Developer News Updated: 02/04/2024

Construction progress update of The Habitat Binh Duong – Phase 3 as at 1 April 2024

Construction status of The Habitat Binh Duong project – Phase 3 is updated as at 01/04/2024:

I. Building Structure: Completed

II. Finishing Part:

  • Block C1, C2, C3

Building wall : F1- Roof

Plastering: F2- Roof

Waterproofing: F2- Roof

Screeding floor: F2-F18

Aluminum door frame installation work: F3-F18

Installation of railings and steel louver: F3-F18

Tiling work: F3- F6

  • Block D1, D2, D3

Building Wall: F1- F18

Plastering: F2 – F18

Waterproofing: F3- Roof

Screeding floor: F3 – F15

Aluminum door frame installation work: F3- F18

Installation of railings and steel louver: F3-F14