Developer News Updated: 03/01/2025

Construction progress update of The Habitat Binh Duong – Phase 3 as at 1 January 2025

Construction status of The Habitat Binh Duong project – Phase 3 is updated as at 01/01/2025:

I. Building Structure: Completed

II. Finishing Part:

  • Block C1, C2, C3

Building wall : Completed

Plastering: Completed

Waterproofing: Completed

Screeding floor: Completed

Aluminum door frame installation work: Completed

Installation of railings and steel louver: Completed

Tiling work: F2- F18

Interior: F2-F18

Install stair railing: Completed

  • Block D1, D2, D3

Building Wall: Completed

Plastering: Completed

Waterproofing: Completed

Screeding floor: Completed

Aluminum door frame installation work: F3-F18

Installation of railings and steel louver: Completed

Tiling work: F2- F18

Aluminum door frame installation work: F3- F18

Installation of railings and steel louver: Completed

Interior: F2-F18

Install stair railing: Completed