Construction status of The Habitat Binh Duong project – Phase 3 is updated as at 01/06/2023:

  • Block C1, C2, C3: Floor 1-16: 100%; Floor 17: 80%; Floor 18: 50%; Roof: 30%
  • Block D1, D2, D3: Floor 1-16: 100%; Floor 17: 80%; Floor 18: 30%; Roof: 30%