Developer News Updated: 02/03/2023

Construction progress update of The Habitat Binh Duong – Phase 3 as at 01 Mar 2023

Construction status of The Habitat Binh Duong project – Phase 3 is updated as at 01/03/2023:

  • Block C1, C2, C3: Floor 1-11: 100%; Floor 12: 80%; Floor 13: 55%; Floor 14: 40%; Floor 15: 35%
  • Block D1, D2, D3: Floor 1-12: 100%; Floor 13: 30%