Construction progress update of The Habitat Binh Duong – Phase 3 as at 1 December 2023

Construction status of The Habitat Binh Duong project – Phase 3 is updated as at 01/12/2023:

I. Building Structure: Completed

II. Finishing Part:

  • Block C1, C2, C3

Building wall : F1-roof

Plastering: F2-F17

Waterproofing: F2-F15

Screeding floor: F2-F14

  • Block D1, D2, D3

Building Wall: F2-F18

Plastering: F3-F16

Waterproofing: F3-F10

Screeding floor: F4-F8