Developer News Updated: 01/02/2024

Construction progress update of The Habitat Binh Duong – Phase 3 as at 1 February 2024

Construction status of The Habitat Binh Duong project – Phase 3 is updated as at 01/02/2024:

I. Building Structure: Completed

II. Finishing Part:

  • Block C1, C2, C3

Building wall : F1- Roof

Plastering: F2- Roof

Waterproofing: F2-F18

Screeding floor: F2-F18

  • Block D1, D2, D3

Building Wall: F1-F18

Plastering: F3-F18

Waterproofing: F3-F15

Screeding floor: F3-F15