Developer News Updated: 03/07/2024

Construction progress update of The Habitat Binh Duong – Phase 3 as at 1 July 2024

Construction status of The Habitat Binh Duong project – Phase 3 is updated as at 01/07/2024:

I. Building Structure: Completed

II. Finishing Part:

  • Block C1, C2, C3

Building wall : Completed

Plastering: Completed

Waterproofing: F2- Roof

Screeding floor: F1-F18

Aluminum door frame installation work: F2-F18

Installation of railings and steel louver: Completed

Tiling work: F2- F18

  • Block D1, D2, D3

Building Wall: Completed

Plastering: F1 – F18

Waterproofing: F3- Roof

Screeding floor: F2 – F18

Aluminum door frame installation work: F3-F18

Installation of railings and steel louver: Completed

Tiling work: F2- F18

Aluminum door frame installation work: F3- F18

Installation of railings and steel louver: Completed