Construction status of The Habitat Binh Duong project – Phase 3 is updated as at 01/10/2024:
I. Building Structure: Completed
II. Finishing Part:
Building wall : Completed
Plastering: Completed
Waterproofing: F2- Roof
Screeding floor: F1-F18
Aluminum door frame installation work: F1-F18
Installation of railings and steel louver: Completed
Tiling work: F2- F18
Interior: F2-F18
Install stair railing: Completed
Building Wall: Completed
Plastering: F1 – F18
Waterproofing: F3- Roof
Screeding floor: F2 – F18
Aluminum door frame installation work: F3-F18
Installation of railings and steel louver: Completed
Tiling work: F2- F18
Aluminum door frame installation work: F3- F18
Installation of railings and steel louver: Completed
Interior: F2-F18
Install stair railing: Completed