Construction progress update of The Habitat Binh Duong – Phase 3 as at 15 May 2023

Construction status of The Habitat Binh Duong project – Phase 3 is updated as at 15/05/2023:

  • Block C1, C2, C3: Floor 1-16: 100%; Floor 17: 40%; Floor 18: 30%; Roof: 30%
  • Block D1, D2, D3: Floor 1-16: 100%; Floor 17: 20%