Construction progress update of The Habitat Binh Duong – Phase 3 as at 15 October 2022

Construction status of The Habitat Binh Duong project – Phase 3 is updated as at 15/10/2022:

  • Block C1, C2, C3: Floor 1-5: 100%; Floor 6: 80%; Floor 7: 30%

  • Block D1, D2, D3: Floor 1-4: 100%; Floor 5: 40%