Developer News Updated: 18/10/2023

Construction progress update of The Habitat Binh Duong – Phase 3 as at 15 October 2023

Construction status of The Habitat Binh Duong project – Phase 3 is updated as at 15/10/2023:

I. Building Structure: Completed

II. Finishing Part:

  • Block C1, C2, C3

Building wall : F2-F18

Plastering: F2-F14

Waterproofing: F2-F11

  • Block D1, D2, D3

Building Wall: F3-F18

Plastering: F3-F11