Construction progress update of The Habitat Binh Duong – Phase 3 as at 30 November 2022

Construction status of The Habitat Binh Duong project – Phase 3 is updated as at 30/11/2022:

  • Block C1, C2, C3: Floor 1-7: 100%; Floor 8: 70%; Floor 9: 40%; Floor 10: 30%
  • Block D1, D2, D3: Floor 1-7: 100%; Floor 8: 20%